Update #6: Progress!

2/26/2025

 
Picture
  • Footings for the building have all been poured.
  • The first floor of the north wing has all of the concrete slab poured and the floor joist for the second floor is almost complete.  
  • Dirt work and excavation is currently underway for the outdoor amphitheater.
  • Observers will see the building in the early stages progressing in stages from the north wing to the south wing.  
  • Almost all of the infrastructure (storm drainage, sewer, fire hydrants, fiber optics, electric) has been completed. 
  • All vertical columns have been erected. 
  • The second-story floor panels will begin to be installed to make ready for the concrete floor pour.
  •  The elevator pit has been poured.
  • The cafeteria stage, steps, and ramp has been poured.
  • Exterior framing will continue. 

Comments are closed.

    Archives

    April 2025
    February 2025
    October 2024
    August 2024
    July 2024
    June 2024
    May 2024

    Categories

    All

    RSS Feed

Details

Video tour

Support

Questions?


Questions about the new High School that aren't answered here?
Contact [email protected].

  • Home
  • New High School
    • About
    • Virtual Tour
    • Progress Updates
    • FAQs for current families
  • Giving
    • Buy a Brick
    • Online Donation
    • In-Kind Donations
    • Staff Payroll Deduction
  • Contact
  • HOPE
    • HCSNM.org
    • HOPE Christian High School
    • Apply Now